Labour Budget & Production Target Control

The financial and performance guardrails for every task — estimate, bonus target, and internal budget, kept distinct.

Scopes Tracked
5
0This month
Over Internal Budget
1
1This month
Company Forecast Variance
-1.9%
0.4%This month
Bonus-Eligible Scopes
4
0This month

Budgets & Targets

5 scopes
ScopeEstimatedBonus TargetInternal BudgetActualForecastVarianceStatus
Framing — Building 3
Task
160 hrs150 hrs175 hrs142.5 hrs168 hrs-7 hrsActive
Prefab Wall Assembly
Task
95 hrs88 hrs100 hrs89.0 hrs101 hrs+1 hrsActive
Foundation Pour — Building 11
Task
280 hrs260 hrs290 hrs312.5 hrs330 hrs+40 hrsActive
Wildstone · Building 8
Building
1,420 hrs1,320 hrs1,500 hrs1,180 hrs1,460 hrs-40 hrsActive
Wildstone Townhomes
Project
18,600 hrs17,200 hrs19,500 hrs11,540 hrs19,120 hrs-380 hrsActive