Historical Estimating Tool
Data-driven recommendations from historical production data instead of gut-feel numbers.
Active Estimates
5
1This month
Historical Records
1,248
34This month
Low Confidence
1
1This month
Avg. Estimate Accuracy
94.1%
0.6%This month
Estimates
5 estimates| Task Type | Quantity | Historical Median | Recommended | Estimator Entered | Confidence | Result / Override | ||
|---|---|---|---|---|---|---|---|---|
Framing — Townhome Unit EST-2201 · Riverside Commons | 24 units | 148 hrs/unit · n=34 | 152 hrs/unit | 160 hrs/unit | High | Pending | ||
Foundation Pour — Standard EST-2200 · Foothills Estates | 18 buildings | 265 hrs/bldg · n=21 | 270 hrs/bldg | 270 hrs/bldg | High | Pending | ||
Siding Install — Exterior EST-2199 · Wildstone Townhomes | 12 buildings | 195 hrs/bldg · n=9 | 205 hrs/bldg | 200 hrs/bldg | Medium | +204 hrs actual | ||
Prefab Wall Assembly EST-2198 · Wildstone Townhomes | 60 walls | 1.4 hrs/wall · n=112 | 1.45 hrs/wall | 1.4 hrs/wall | High | 89 hrs actual | ||
Siding Repair — Water Damage EST-2197 · Maple Court | 1 unit | 22 hrs · n=3 | 28 hrs | 20 hrs | Low | Override: client urgency |