Field Exception Tracking

Capture and categorize what stops or slows work, and whether it's recoverable or billable.

Open Delays
2
2This month
Crew-Hours Lost
37.0 hrs
4%This month
CO Candidates
1
1This month
Resolved This Week
2
2This month

Delays & Blockers

5 events
TaskCategoryStartLost Crew-HoursResponsibleRecoverableCO CandidateStatus
Foundation Pour — Building 12
DLY-210 · Wildstone Townhomes
Material DelayAug 3, 06:30 AM14.0SupplierReviewNoOpen
Siding Install — Building 9
DLY-209 · Wildstone Townhomes
Equipment ShortageAug 3, 08:00 AM6.5CompanyNoNoOpen
Siding Repair — Unit 14
DLY-208 · Maple Court
Design ClarificationAug 2, 09:15 AM3.0ClientYesYesDisputed
Framing — Building 1
DLY-207 · Wildstone Townhomes
WeatherJul 30, 07:00 AM8.0OtherYesNoResolved
Interior Trim — Building 1
DLY-206 · Birchwood Row
Prior Trade IncompleteJul 29, 10:30 AM5.5CrewNoNoResolved