Pre-Work Readiness Checks

Catch delays before they happen: drawings, materials, tools, safety, and crew skills checked before work starts.

Ready to Start
2
1This month
Not Ready
2
2This month
Conditional
1
0This month
Checks This Week
18
3This month

Readiness Checks

5 checks
TaskDrawingsMaterialsTools & EquipmentSafetyOverall StatusChecked By
Framing — Building 4
Wildstone · Bldg 4
AvailableDeliveredAvailableAcceptableReady
S. Grewal
Aug 3, 04:10 PM
Foundation Pour — Building 12
Wildstone · Bldg 12
AvailablePendingAvailableAcceptableNot Ready
S. Grewal
Aug 3, 02:45 PM
Siding Install — Building 9
Wildstone · Bldg 9
AvailableDeliveredMissingAcceptableConditional
R. Dhillon
Aug 3, 11:20 AM
Interior Trim — Building 2
Birchwood Row · Bldg 2
AvailableDeliveredAvailableAcceptableReady
K. Anand
Aug 2, 09:00 AM
Siding Repair — Unit 14
Maple Court · Unit 14
MissingDeliveredAvailableReview RequiredNot Ready
R. Dhillon
Aug 2, 08:15 AM